Saturday, November 30, 2013

Energy Audit Case Study: Tire Factory Sri Lanka





Company Description
ABC* is one of the leading rubber products factories in Sri Lanka producing tires and retreading small to large tyres using cold and hot processes. The installed annual retreading capacity of the hot process is 400,000 tires and of the cold process 135,000 tyres. Annual productions of the main products are as follows:
- Retreading – Hot 120,000 tires
- Retreading – Cold 46,000 tires
- Vaerling process - 55,000 tires
- Compounding-  9,600 tires
- Tyres manufacturing - 4,000 tires
- Rubber products - 600 tons

Process Description
The company consists of a large number of subsidiary factories using different processes to
manufacture and retread tires and to manufacture rubber products.
- Material preparation: The common process for most of the factories is material preparation.
Raw rubber, mostly in the form of sheets (RSS), is mixed with additives in a Bambury
mixer or calendar.
- Tyre making: Tyre manufacturing for small vehicles consists of several steps:
· Main process – tyre making: Raw rubber compound is warmed, cut and conveyed to an
extruder where it is formed into flat sheets. The tire is built on a mould using the rubber
sheets.
· Sub process 1 - Bead wire ring making
· Sub process 2 - Bias cutting process
· Sub process 3 - Air bag making
- Tyre retreading – Hot process:
· Initial inspection
· Buffering
· Application of new rubber
· Vulcanization
· Final inspection
- Tyre retreading - Cold process: This process is performed below 1000C. The tread used in
this process is cured before retreading and fixed on the carcass.


Continuous improvement
The company has taken several initiatives to ensure energy efficiency improvements will continue. Some important ones are:
· Appointment of a Project and Development Engineer to focus on energy management
· Increased communication to factory staff about energy efficiency options and assessments

The focus areas selected
· Boiler and steam distribution system: five options identified and four implemented
· Compressed air production and distribution system: three options identified and still under investigation
· Rubber Products Division (RPD), where numerous options were generated:
- Main tyre making: 13
- Bead wire process: 11
- Process cutting: 74
- Air bag making: 8
· Electricity supply system
- For six of the implemented options for which results were measured (see table below), the total investment costs were US$ 49,080, annual savings were US$ 84,764 and total payback was 7 months
- For options implemented, the total energy reductions were 521 MW and 173 kilo-liters furnace oil per year resulting in 607 ton CO2 emission reductions per year

OPTIONS IMPLEMENTED
FOCUS AREA/
OPTION
FINANCIAL
FEASIBILITY
ENVIRONMENT
AL BENEFITS
COMMENTS
Compressed air supply system:
Replacement of inefficient compressor with two screw type
compressors

- Investment costs: US$ 29,500.
§ Operating costs: lower than in old situation but not quantified
§ Cost savings: US$ 43,137 /yr
§ Payback period: 8 months
§ Electricity
saving: 500
MW/yr
§ GHG emission
reduction: 102
tCO2/yr
Working environment in the compressor room
has improved due to
lower noise and ambient temperature levels
Boiler and steam distribution system: Improved steam system
efficiency through:
§ Boiler maintenance
§ Leak repairs
§ Pipeline insulation
§ Investment:: US$
13,400
§ Cost savings:
US$ 22,315 /yr
§ Payback period:
7 months

§ Furnace oil savings: 98,400 l/yr
§ GHG emission reductions: 303 tCO2/yr
§ Reduction of NOx, particulates

§ Water reduction
The implementation
of these options will
continue as part of a
steam management
program

Boiler and steam
Distribution system: Recover heat from boiler flue gas to preheat combustion air
§ Investment: US$ 300
§ Cost savings: US$ 600 /yr
§ Payback period: 6 months

§ Fuel savings:
1,044 l/yr
§ GHG emission
reduction: 3.2
tCO2 /yr

Option is being implemented. The company boiler room and maintenance staff were involved in the
installation
Rubber Products Division (RPD):
Insulation of
§ Steam Pipelines
§ Tyre moulds of
Vulcanization/Curing Process
§ Investment:US$ 1,480
§ Cost savings: US$ 1,380
§ Payback period: 1 year
§ Furnace oil savings: 6,000 l/yr
§ GHG emission reduction: 18 tCO2 /yr
The company is continuously
repairing insulation and leaks
Working conditions improved due to reduced heat loss
Rubber Products
Division (RPD): Condensate recovery
§ Investment: US$ 3,200
§ Operating costs:
US$ 1,200
§ Cost savings: US$ 15,456 /yr
§ Payback period: 4 months
§ Furnace oil saving : 67,200 liters/yr
§ GHG emission reduction: 207 tCO2/yr

The company implemented this option but all figures are still
expected costs and
savings
Rubber Products
Division (RPD):
Compressed air leak
survey and leak
repair
§ Investment: not
quantified but very low
§ Operating costs: ongoing
§ Cost savings:
US$ 1,876/yr
§ Payback period:
estimated 1 month
§ Electricity
savings: 21,432
kWh/yr
§ GHG emission
reduction: 4.4
tCO2/yr

Rubber Products
Division (RPD):
Electricity saving
through waste
reduction of nylon
thread and rubber
compound
§ Investment: not
provided
§ Cost savings:
US$ 1,977

§ Electricity
savings: 28
MW/yr
§ GHG emission
reduction =5.7
tCO2/yr

Not yet
implemented: all
figures are expected
costs and savings.
Preliminary energy
audit completed
Electrical Supply
system:
Installation of load
demand indicators

§ Investment: not
provided
§ Cost saving: US$
6,336

§ Energy savings:
2112 kVA
Not yet implemented: all
figures are expected
costs and savings.
Preliminary energy
audit done
Electrical Supply
system:
Power demand management and
installation of electricity sub meters at Bambury
Mixer
§ Investment: not
provided (for meter)
§ Cost saving: US$
7,920
§ Payback period:
not provided

§ Demand peak
reduction: 2,620 kVA
§ Energy savings:
none
§ GHG emission
reductions: none

Not yet implemented: all
figures are expected
costs and savings.
Preliminary energy
audit done


- Energy  Efficiency Asia Project

No comments:

Post a Comment