Company
Description
ABC* is one of the leading rubber products factories in
Sri Lanka producing tires and retreading small to large tyres using cold and
hot processes. The installed annual retreading capacity of the hot process is
400,000 tires and of the cold process 135,000 tyres. Annual productions of the
main products are as follows:
- Retreading – Hot 120,000 tires
- Retreading – Cold 46,000 tires
- Vaerling process - 55,000 tires
- Compounding-
9,600 tires
- Tyres manufacturing - 4,000 tires
- Rubber products - 600 tons
Process
Description
The
company consists of a large number of subsidiary factories using different
processes to
manufacture
and retread tires and to manufacture rubber products.
- Material preparation:
The common process for most of the factories
is material preparation.
Raw
rubber, mostly in the form of sheets (RSS), is mixed with additives in a
Bambury
mixer
or calendar.
- Tyre making: Tyre manufacturing for small vehicles consists of several
steps:
· Main process – tyre making: Raw rubber
compound is warmed, cut and conveyed to an
extruder
where it is formed into flat sheets. The tire is built on a mould using the
rubber
sheets.
· Sub process 1 - Bead wire ring making
· Sub process 2 - Bias cutting process
· Sub process 3 - Air bag making
- Tyre retreading –
Hot process:
· Initial inspection
· Buffering
· Application of new rubber
· Vulcanization
· Final inspection
- Tyre retreading -
Cold process: This process is performed below 1000C. The tread used in
this process is
cured before retreading and fixed on the carcass.
Continuous improvement
The
company has taken several initiatives to ensure energy efficiency improvements
will continue. Some important ones are:
· Appointment of a Project and Development
Engineer to focus on energy management
· Increased communication to factory staff
about energy efficiency options and assessments
The focus areas selected
· Boiler and steam distribution system: five
options identified and four implemented
· Compressed air production and distribution
system: three options identified and still under investigation
· Rubber Products Division (RPD), where numerous
options were generated:
-
Main tyre making: 13
-
Bead wire process: 11
-
Process cutting: 74
-
Air bag making: 8
· Electricity supply system
- For six of the implemented options for which
results were measured (see table below), the total investment costs were US$
49,080, annual savings were US$ 84,764 and total payback was 7 months
- For options implemented, the total energy
reductions were 521 MW and 173 kilo-liters furnace oil per year resulting in
607 ton CO2 emission reductions per year
OPTIONS IMPLEMENTED
FOCUS AREA/
OPTION
|
FINANCIAL
FEASIBILITY
|
ENVIRONMENT
AL BENEFITS
|
COMMENTS
|
Compressed air supply system:
Replacement of inefficient compressor with two screw
type
compressors
|
- Investment
costs: US$ 29,500.
§ Operating
costs: lower than in old situation but not quantified
§ Cost
savings: US$ 43,137 /yr
§ Payback
period: 8 months
|
§ Electricity
saving: 500
MW/yr
§ GHG
emission
reduction: 102
tCO2/yr
|
Working environment in the compressor room
has improved due to
lower noise and ambient temperature levels
|
Boiler and steam distribution system: Improved steam
system
efficiency through:
§ Boiler
maintenance
§ Leak
repairs
§ Pipeline
insulation
|
§ Investment::
US$
13,400
§ Cost
savings:
US$ 22,315 /yr
§ Payback
period:
7 months
|
§ Furnace
oil savings: 98,400 l/yr
§ GHG
emission reductions: 303 tCO2/yr
§ Reduction
of NOx,
particulates
|
§ Water
reduction
The implementation
of these options will
continue as part of a
steam management
program
|
Boiler and steam
Distribution system: Recover
heat from boiler flue gas to preheat combustion air
|
§ Investment:
US$ 300
§ Cost
savings: US$ 600 /yr
§ Payback
period: 6 months
|
§ Fuel
savings:
1,044 l/yr
§ GHG
emission
reduction: 3.2
tCO2 /yr
|
Option is being implemented. The company boiler room
and maintenance staff were involved in the
installation
|
Rubber Products Division (RPD):
Insulation of
§ Steam
Pipelines
§ Tyre
moulds of
Vulcanization/Curing Process
|
§ Investment:US$
1,480
§ Cost
savings: US$ 1,380
§ Payback
period: 1 year
|
§ Furnace
oil savings: 6,000 l/yr
§ GHG
emission reduction: 18 tCO2 /yr
|
The company is continuously
repairing insulation and leaks
Working conditions improved due to reduced heat loss
|
Rubber Products
Division (RPD): Condensate
recovery
|
§ Investment:
US$ 3,200
§ Operating
costs:
US$ 1,200
§ Cost
savings: US$ 15,456 /yr
§ Payback
period: 4 months
|
§ Furnace
oil saving : 67,200 liters/yr
§ GHG
emission reduction: 207 tCO2/yr
|
The company implemented this option but all figures are
still
expected costs and
savings
|
Rubber Products
Division (RPD):
Compressed air leak
survey and leak
repair
|
§ Investment:
not
quantified but very low
§ Operating
costs: ongoing
§ Cost
savings:
US$ 1,876/yr
§ Payback
period:
estimated 1 month
|
§ Electricity
savings: 21,432
kWh/yr
§ GHG
emission
reduction: 4.4
tCO2/yr
|
|
Rubber Products
Division (RPD):
Electricity saving
through waste
reduction of nylon
thread and rubber
compound
|
§ Investment:
not
provided
§ Cost savings:
US$ 1,977
|
§ Electricity
savings: 28
MW/yr
§ GHG
emission
reduction =5.7
tCO2/yr
|
Not yet
implemented: all
figures are expected
costs and savings.
Preliminary energy
audit completed
|
Electrical Supply
system:
Installation of load
demand indicators
|
§ Investment:
not
provided
§ Cost
saving: US$
6,336
|
§ Energy
savings:
2112 kVA
|
Not yet implemented: all
figures are expected
costs and savings.
Preliminary energy
audit done
|
Electrical Supply
system:
Power demand management and
installation of electricity sub meters at Bambury
Mixer
|
§ Investment:
not
provided (for meter)
§ Cost
saving: US$
7,920
§ Payback
period:
not provided
|
§ Demand
peak
reduction: 2,620 kVA
§ Energy
savings:
none
§ GHG
emission
reductions: none
|
Not yet implemented: all
figures are expected
costs and savings.
Preliminary energy
audit done
|
- Energy Efficiency Asia Project
No comments:
Post a Comment